April 2026
12% · Foundations · lower deck pour
Foundations down, first wall up
Eastern foundation slab poured in the second week. Beat schedule by four days, which is the kind of small win that means a lot when you're building in Bali in the wet season.
Volcanic stone arrived from East Java early. Nizar spent a morning with the masons working out how to lay it without sealing it — volcanic stone needs to breathe, and we want this house to age the way the cliffs do, not the way bad concrete does.
South wall went up Friday. From the road it still looks like nothing. From the lower deck looking back, you can see the shape of the whole thing now.
Honest stuff: rain killed the access road twice. We rerouted. Everything else on track. May we go vertical.